From: City of Morgan HillIf you would like to receive a notification when The Scoop is published each week, please subscribe to the Notify Me list (select The Scoop), via the following link https://www.morgan-hill.ca.gov/list.aspx
New items or items with information updated this week have asterisks “**” in front of them.
Traffic Delays or Closures in the Weeks Ahead:
-East Dunne Avenue Rehabilitation Project
Contractor will begin lowering utility boxes starting on July 5th and work their way westbound from near Anderson Lake Bridge (City limit line) and head westbound on Dunne Avenue. Traffic control will be implemented beginning July 5th. The project will continue through the end of September.
**2022 Pavement Rehabilitation Project
The City of Morgan Hill has an ongoing Pavement Rehabilitation Program intended to address the City's pavement rehabilitation needs. Throughout the next several months, you may see work in your neighborhood or along your regular route of travel throughout Morgan Hill. Teichert Construction and City of Morgan Hill will be starting our East Dunne Avenue Rehabilitation Project and 2022 Pavement Rehabilitation project on July 5, 2022. The work will begin from 7am to 5pm Monday through Friday. Once paving work is completed, crews will start utility cover preparation and restoration, as well as final striping.
Week of 7/11 to 7/15 from 7am to 5pm
7/11/22
Grind and Pave East Dunne from City limits to Jackson Oaks Drive
Grind pavement at Jackson Oaks Drive
Lower Manhole Covers at Rustling Oaks Court in preparation of Grind and Paving work
Lower Manhole Covers at Oakridge Court in preparation of Grind and Paving work
7/12/22
Grind and Pave East Dunne from City limits to Jackson Oaks Drive
Grind Pavement at Jackson Oaks Drive
Lower Manhole Covers at Rustling Oaks Court in preparation of Grind and Paving work
Lower Manhole Covers at Oakridge Court in preparation for Grind and Paving work
Pavement Marking Removal at the following locations:
East Dunne Avenue
Hill Road
Thomas Grade
Jackson Oaks Drive and side streets
Oakridge Dr.
Condit Road
Vineyard Blvd
Mast St.
Church Street
7/13/22
Wedge Grind edges of East Dunne Avenue from Flaming Oaks Drive to Hill Road
Wedge Grind edges of Hill Road from Dunne Avenue to Sundance Drive
Pavement Repairs at Jackson Oaks Drive
Grind and Pave portion of Oakridge Court
Lowering Manhole Covers at Murphy Avenue from Barrett Avenue to San Pedro Avenue in preparation of Grind and Pave
Lowering Manhole Covers at Hill Road from Sundance Drive to San Pedro Avenue in preparation of Grind and Pave
7/14/22
Wedge Grind edges of East Dunne Avenue from Flaming Oaks Drive to Hill Road
Pave Jackson Oaks Drive
Lower Manhole covers at Vineyard Blvd from Mast Avenue to Tennant Avenue
7/15/22
Lower Manhole covers at Vineyard Blvd from Mast Avenue to Tennant Avenue
Pave Jackson Oaks Drive
Click Here For More Information