Edit

Town Of Lexington - Center Streetscape Project Update

Government and Politics

July 18, 2022

From: Town Of Lexington

Construction Update: Week of July 18-22

Work zones on the north side of the street are substantially complete. Remaining work includes the installation of light poles, benches, bike racks and plantings.

Work zones will occur along the south side of the street from:

-Work Zone 3A - Kandi Nails to Muzzy Street – Concrete mud slab & brick walking surface

-Work Zone 3B & 4A - The old Panera at 1684 Massachusetts Avenue to Waltham Street – Sidewalk Reconstruction

-Work Zone 4B – Muzzey Street to Waltham Street – Sidewalk Demolition 

See the current workzone maps. 

Outdoor dining on the north side of the street will be re-opened fully.

As always, access to businesses will REMAIN OPEN AT ALL TIMES. Please remember to check our interactive map for the latest construction work zones.